artisans of Baraka prepare the relocation 26 families impacted by the constrction buildings

The relocation of the 26 families impacted by the project « Cité Baraka » had a huge delay and that is why the Baraka development committee in relation with the artisans of Baraka decided to get their hands dirty by proposing to build much cheaper Baraques.
Baraka craftsmen, especially carpenters, masons and electricians are hard at work for the realization of 78 Baraques.rps20180619_212804

This work is also facilitated by the Municipality of Sicap Liberty with the unfailing support of the Mayor Sir Sathie Agne who has the means to clear the occupants of the road and to clear the site which was made of large stones.
As a reminder, the space located on the main road at the entrance to Baraka was chosen to build the first 20 barracks and relocate families located southeast of the site. This will allow the contractor to properly continue building construction.rps20180619_212550

This « Cité Baraka » project is strongly supported by the State of Senegal through the Ministry of Urban Renewal of Housing and Living Environment which has set up a steering committee to facilitate the implementation of the project.rps20180619_212506

It is in this context that the chairman of the said committee, Mrs Soumaré, makes a weekly visit to the site to see the progress of the work.
Baraka artisans will never stop thanking the YOU Foundation for building capacity by empowering them in their fields.
According to them it is this training which motivated their implication in the proposal of the construction of barracks to relocate the 26 affected families.
Below are some photos of the project for the relocation of families impacted by the project:

 

The President of the Steering Committee of the « Cité Baraka » Project is monitoring the construction site

The president of the steering committee of the « Cité Baraka » project Ms. Soumaré paid a visit to the construction site in Baraka on Thursday, May 24, 2018. This visit was facilitated by the team of HOPE’87 Senegal, a local partner of the YOU Foundation in Germany and the Baraka Development Committee.
As a reminder, this steering committee was set up by the Ministry of Urban Renewal of Housing and Living Environment to facilitate the implementation of this project which is very dear to Mrs Ohoven.
Ms. Soumaré discussed with the site manager Talla Diop and the director of operations Mr Kane of the company IC Suarl who specified that the site is in phase of installation with the preliminary orders.rps20180530_101439

This is the sand dune site supply for 20 m3, 3/8 basalt concrete for 20m3, 8/16 basalt concrete for 8m3, cement for 4 tonnes, 8 for 3 iron, 5 tons, iron of 10 for 1.5 tons, iron of 12 for 2 tons and iron of 14 for 0.3 tons.rps20180530_101523

According to Talla Diop site manager, the current job is to dig holes called building footings for a depth of 2m and a width of 1.5m to 2.20m.rps20180530_101510

For each building, only half of the footings were dug.
Workers who are on average 20 people a day are confronted at the moment of the work with the presence of the connecting pipes of the ONAS (National Office of the Sanitation of Senegal). The chair of the steering committee suggested that IC SUARL approach the ONAS to transfer the connecting pipes.rps20180530_101409

After the site visit, the chair of the steering committee held a working session with the team of IC SUARL, the members of the Baraka Development Committee and the HOPE’87 team in Senegal. During this meeting, Mrs. Soumaré informed the company IC SUARL that the work is late and will be late compared to the delivery time if no solution is found.
Site manager Mr. Diop responded by noting that the relocation of affected families had slowed down the work considerably.
This is how the Baraka Development Committee, in connection with the craftsmen of Baraka, decided to get their hands dirty by proposing to build much cheaper Baraques.rps20180530_101425

This initiative is taken on a consensual basis with the 26 affected families so that the work can be done in good conditions.

The visit of Mrs. OHOVEN in Baraka

This Wednesday, on May 25th, the population of Baraka received a visit from Madame OHOVEN of YOU FOUNDATION and their partners, accompanied by a former Senegalese international football player.

Continuer la lecture de The visit of Mrs. OHOVEN in Baraka

Minutes of the meeting between the people of Baraka and the steering committee of the Baraka rehabilitation project.

A meeting between the actors involved in the reconstruction of Baraka namely the population, the project steering committee and HOPE87 took place in our neighborhood this 25th of April, 2016. This meeting was held on Baraka’s football field at 5 p.m. GMT. We will present to you the result of exchanges between the different actors.

Continuer la lecture de Minutes of the meeting between the people of Baraka and the steering committee of the Baraka rehabilitation project.